Black Friday in the warehouse: How three logistics teams master the peak

On preparation, staffing and robot fleets when orders explode.

eveneven·16. November 2026·8 min read
even promotional graphic for Black Friday: a man in a suit stands at a loss in a chaotic, burning warehouse full of parcels.

In a nutshell

45,000 orders a day suddenly become 65,000, a warehouse processes ten times its normal throughput in a single Sunday, and an AutoStore system gains two hours of productivity simply because someone adjusted the robots' charging cycles. Black Friday and Black Week, which now extends almost seamlessly into Cyber Week, confront warehouses with challenges that have little in common with normal day-to-day operations. Drawing on practical insights from Marco Pavicic, Managing Director of Elandia Fulfillment GmbH, Stefanie Schlichting, Head of Logistics at HAGEL-SHOP, and Cihan Yasar, Managing Director at The Quality Group, we show how differently teams can respond to the same pressure.

On 27 November it is Black Friday again. For retail, that marks the start of the most revenue-intensive period of the year. For the logistics operations behind it, the weeks that follow rank among the most demanding of the year. Orders multiply within just a few days, warehouses must ramp up capacities they simply do not need for the other eleven months, and in the end every parcel still has to go out on time. How companies prepare for these weeks depends heavily on the infrastructure and the team they have available. Three voices from practice illustrate how differently the answers can look when the underlying problem is the same: more orders than the system can handle under normal conditions.

Preparation begins months in advance, not during Black Week itself

Anyone who only starts thinking about the peak in November is already late. All three interview partners confirm this independently of one another. Marco Pavicic, Managing Director of Elandia Fulfillment GmbH, relies above all on solid forecasts as a planning basis. His advice to others preparing for a peak for the first time: plan with slightly more staff and capacity rather than cutting it too close. At Elandia, orders during Black Week are processed strictly in the sequence they arrive, oldest first, rather than being sorted by priority. The team has already taken one lesson from this year: temporary workers should be scheduled and onboarded earlier next year.

Stefanie Schlichting, Head of Logistics at e-commerce beauty retailer HAGEL-SHOP, is even more specific. She says the lead time must begin in late summer: "You really have to start in August or September if you want to survive Black Friday, if you genuinely want a warehouse that runs smoothly." At HAGEL-SHOP this means in concrete terms: stock is deliberately built up before Black Week so that as little inbound goods handling as possible falls during the busy phase, allowing the team to focus entirely on picking, packing and shipping. Deliveries from suppliers are also staggered so that several large inbound shipments do not hit the floor simultaneously. The forecasts themselves have also grown more sophisticated: HAGEL-SHOP calculates using prior-year figures, the usual growth rate and additionally the effects of new product ranges, for example when an item from a recently introduced category performs surprisingly well.

Stefanie has also made adjustments to the technology itself: HAGEL-SHOP operates an AutoStore system where the number of ports is the real performance constraint. During the summer she therefore adjusted the robots' charging cycles. They now head to the charging station at 35 to 50 percent battery level instead of the previous 40 to 60 percent. As a result they keep running longer into the afternoon before they all want to charge at the same time, a gain of around two hours of productivity per day. In addition, the operation switched from a three-shift to a two-shift system: in her experience an AutoStore needs around four hours of downtime to pre-sort orders and pre-charge itself. Running continuous night shifts, the system performed noticeably worse. Since the switch, operations have been running more smoothly than before under three-shift working, with less wear on the robotics at the same time.

For Cihan Yasar, Managing Director at The Quality Group, the peak phase starts even earlier: "For me a peak phase does not begin with the first rush. It begins at hour zero. That is when you see how well we have done our homework: whether the IT infrastructure holds up, whether the staff are motivated, whether the robots keep going." His site in Elsdorf operates as an e-commerce fulfillment center and handles, among others, the brand More Nutrition. Under normal conditions, 20,000 to 30,000 orders go out there per day. On one Sunday during the current Black Week that figure exceeded 280,000, a factor of 10. On average the team is currently dispatching 100,000 to 105,000 orders daily, the equivalent of 600,000 to 700,000 individual items.

Start sourcing in good time and train people far enough in advance that they have already developed a routine. Nobody has the time during peak season to onboard ten people at once.
Stefanie Schlichting, Head of Logistics at HAGEL-SHOP

People in the peak: temporary workers, core team or both

On the staffing question, the three companies take noticeably different approaches. Elandia relies on temporary workers, but plans to book and onboard them earlier in future so that routines do not still need to be built during the rush.

HAGEL-SHOP, by contrast, almost entirely avoids conventional temporary staffing. Stefanie instead relies on a fixed pool of casual workers that has grown over years and is mobilised via a WhatsApp group when needed. The advantage: these workers already know the products and processes. Her advice to anyone new to peak season who depends on external staffing agencies: "Start sourcing in good time and train people far enough in advance that they have already developed a routine. Nobody has the time during peak season to onboard ten people at once." She also places great importance on transparency with the team: backlogs and daily output are communicated openly, in earlier times on laminated sheets written by hand, today via dashboards, so that everyone develops a feel for when there is genuinely cause for concern.

At The Quality Group, the core team of 400 to 500 employees is supplemented during the peak with additional flex staff, "so that the full burden does not fall on our permanent workforce," as Cihan puts it. The operation runs 24 hours a day, six days a week, deliberately not on Sundays, even though the volume would theoretically permit it. To keep the team motivated, Yasar uses an unusual method: customer feedback is actively shared with staff in real time on a screen in the warehouse. Despite the sheer scale, he sees the greatest challenge in the technical rather than the human dimension: "During the peak we also see whether the WMS can really keep up. Honestly, we still have difficulties there." Access points and IT infrastructure also reach their limits when so many devices are active simultaneously.

When floor space runs out: large-scale automation

How well an automated warehouse can scale with peaks is illustrated most clearly by the development at The Quality Group. The site started with 40 mobile Locus Robotics robots, designed for around 45,000 orders a day, and has grown to nearly 260 robots. The first peak already showed that this was not enough: within just a few weeks the team had to scale up to 60,000 orders and 350 robots, while conveyor technology and packaging automation were still configured for the original capacity. The fleet now runs with more than 480 robots.

Looking back, Cihan cites flexibility above all as the reason why The Quality Group chose mobile robots over a fixed automation solution: the fleet can be expanded when needed and scaled back down just as easily when volume falls, with robots simply being returned. Additional factors include the wide range of article sizes in the product range, from packaging just five centimetres small to a 50-centimetre-long bag of crisps, and the speed of implementation: from contract signature to the first live shipments, The Quality Group needed 90 days. The fact that additional robot capacity can also be rented at short notice is reflected in the contract models: according to Malte Guske, who is responsible for sales in Northern and Western Europe at Locus Robotics, the minimum contract term for peak capacity is one month, while The Quality Group itself typically books for twelve.

Guske explains the limits of such a fleet using two factors: available floor space and IT infrastructure. As a rough rule of thumb for space planning he cites 70 square metres per robot for one-way traffic, 40 square metres for two-way traffic and around 30 square metres when three robots need to pass one another simultaneously. The Quality Group benefits from a wide-aisle warehouse with corridors more than three metres wide, where in some areas as many as five robots can pass side by side. Guske uses an additional benchmark to define who stands to benefit from such a fleet: from around 3,500 order lines per day and eight to ten manual pickers, the investment starts to pay off. Standard projects typically begin with 30 to 40 robots, sometimes with as few as 10 to 15. The warehouse floor space should be at least 1,500 to 2,000 square metres, so that there are walking distances worth shortening in the first place.

Looking back, Cihan would do most things the same way again, above all involving the workforce from the outset and addressing their concerns about job losses early on: the robots did not eliminate any positions, but they significantly reduced the distances employees have to cover, instead of walking across a floor of several tens of thousands of square metres with a picking trolley weighing up to 30 kilograms. The more difficult part was that operations had to get under way before the conveyor technology and high-bay racking were finished, which subsequently required further adjustments to the robot travel routes. Yasar also made a deliberate decision to adopt a single automation technology rather than distributing fast-moving and slow-moving items across different systems, while still keeping a manual backup with conventional picking trolleys available for emergencies.

Conclusion

Three warehouses, three entirely different starting points, and yet the same threads run through every conversation: those who get through Black Week well started planning months earlier, know their numbers and have built in sufficient buffer, whether that buffer comes in the form of additional hands, additional robots or simply more inventory. Automation does not replace any of the other levers. It only shifts where the real limit lies.

The most important learnings for peak season
  1. Start early: preparation for Black Friday begins no later than August or September, not in November.
  2. Better too much than too little: scale up staff and capacity generously rather than calculating too tightly.
  3. Onboard temporary workers in advance: anyone relying on temporary staffing should train those workers before the peak, not during it.
  4. Transparency creates motivation: teams that know their own numbers are more likely to pull together during stressful periods.
  5. Plan for flexible capacity: whether additional robots or temporary workers, Solutions that can be scaled back after the peak prevent costly overcapacity.
Frequently asked questions

These answers were generated with AI.

According to Stefanie Schlichting, Head of Logistics at HAGEL-SHOP, preparation must begin as early as August or September. Anyone who only starts in November is too late, as key measures such as building up inventory levels and onboarding staff require sufficient lead time.